Maintenance Building Replacement
Maintenance Building Replacement Project
We would like to thank everyone for their support throughout the building of the new Maintenance building.
From ground clearing in May 2025 to the internal finishing touches in October, the new building is now fully utilized to store vehicles and our maintenance equipment / supplies.
The 1975 building is only a memory and its removal has opened up outdoor maintenance workspace and additional vehicle parking.
Because of those who donated materials, labour and funds, this project was completed on schedule. The overall cost of the building design, materials and construction were lower than the budget because of the wonderful support from the Beacon faithful.
The only remaining portion of this project is the installation of an additional back up power generator for Beacon. This new generator equipment is expected to be installed in 2025 and will provide backup power for the new maintenance building, Crowsnest and the Wheelhouse / Town Hall.
We praise God for all who prayed for this project and for safety during construction. We are so thankful for those who donated funds, materials and their time constructing this building. A special thank you to Mr. Tok for his oversight and skills during the project.
Please ask Strider for a tour the next time you are at Beacon.
Renovation Details
New Capacity 3750 sq ft - Currently 348 M Sq
2500 sq. ft. of vehicle, equipment and material storage
1250 sq. ft. of heated storage and shop space
Additional parking where the former building was located
Outdoor work area for maintenance projects
REMAINING WORK
Beacon mural on end of Building
Purchase / install backup generator
Generator connection to Crowsnest, Wheelhouse / Townhall
“Let your light shine before others, so that they may see your good works and give glory to your Father who is in heaven.”